National Water Corporation |
El Obied Town Water Pipeline 30km from Bara Basin |
|
1999 |
750000 |
CPECC |
Civil Works for Pump Station (1)extension at Heglig Site |
|
2000 |
350000 |
GNPOC |
Construction of Bantiu Hospital – Unity State (JV) Sudan Pile - Nile Star |
|
2005 |
2800000 |
National Electricity Corporation |
Al Shagara Sub-station-Foundations, concrete road,buildings, towers |
|
2005 |
394897 |
National Electricity Corporation |
GIAD Substation-Foundation, concrete road, buildings, towers |
|
2005 |
1502889 |
WNPOC |
Civil Work for Power Plant in Thar Jath |
|
2006 |
3100000 |
National Electricity Corporatio |
Mahdia Sub-station-Foundations, concrete road, buildings, towers |
|
2006 |
750000 |
GNPOC |
Central Processing Facilities (CPF) JV Sudan Pile – HL Engineering |
|
2006 |
78000000 |
Petrodar |
Marine Terminal (Consortium) Peremba – Sudan Pile - Intec |
|
2007 |
27500000 |
National Electricity Corporation |
Jabel Awlia Rest House: Civil, steel&glass work |
|
2007 |
1788171 |
National Electricity Corporation |
Extension of Oumdurman Sub-station |
|
2007 |
999760 |
National Electricity Corporation |
Singa Sub-Station-Foundations,concrete road, towers |
|
2007 |
7052036 |
GNPOC |
Community Development Project construction |
|
2009 |
4000000 |
GNPOC |
Firewater Ponds Modifications-Concreting & waterproofing |
|
2010 |
4000000 |
GNPOC |
Rehabilitation of Pump Station #4 Air strip |
|
2010 |
490000 |
South Kordofan State Govt |
Talody Air strip-runway, embankment & sub-base work |
|
2012 |
2000000 |
SOS |
Construction of SOS Primary School |
|
2012 |
29600000 |
NEC/BHEL |
Housing Complex (JV) Sudan Pile -China Jiangsu-civil&MED works(62 bldgs) |
|
2012 |
25600000 |
NEC/BHEL |
Foundations, earth work,steel structures and civil work Kosti Power Plant (JV) Sudan Pile -China Jiangsu |
|
2015 |
65000000 |
Ministry of Petroleum |
El Shakhar Dam-concrete spillway, surface basin,elevated water tanks and water pumps |
|
2016 |
5500000 |
GNPOC |
Heglig Airport (Sudan Pile & Nile Star Joint Venture)-runway extension,rehab existing runway |
|
2016 |
9200000 |
NEC/BHEL |
Unloading Railway Area (JV) Sudan Pile -China Jiangsu-Building construction |
|
2016 |
26250000 |
Ministry of Finance |
Rehabilitation of Ministry of Finance Buildings (Consortium) Sudan Pile -China Jiangsu |
|
2018 |
6600000 |
North Omdurman Slaughter House |
Slaughter House (Contract 1, Workshop, Waste Water Treatment Plant Civil Works |
|
2021 |
931717 |
North Omdurman Slaughter House |
Slaughter House Contract 2 (Meat Truck wash, Live Stock Truck Wash, Guard Houses) |
|
2022 |
974345 |
North Omdurman Slaughter House |
Slaughter House Contract 3 (Workshop& Main Building Civil & MEP Works) |
|
Ongoing(60% completed) |
813408 |
Ministry of Finance |
Rehabilitation of Historical Building of Ministry of Finance |
|
2016 |
4000000 |
SUDAN Electricity Holding Company |
Construction of Civil Works of Wind Turbine (Dongola) |
|
2022 |
822700 |
National Medical Supply Fund (NMSF) |
Construction of Medicine Store and administration building in Red Sea, Blue Nile, West Kordofan, Darfur State |
|
2017 |
8750000 |
National Medical Supply Fund (NMSF) |
Construction of Medicine Store and administration building in Khartoum, Northern, Sinnar, Gadarif, South Kordofan |
|
Ongoing |
9046900 |