Client Name |
Name of Project |
Location |
Year Project Duration (month) |
Contract Value USD |
CPECC | Soil Investigation (Pipeline crossings at Nile & Atbara Rivers | North of Khatoum – Atbara |
2 months 1999 |
120,000 |
(JV-Hayder –Newtech) GNPOC | Soil Investigation For Pipeline Access Road bridges. | Um Adara – South Kordofan | 1 month 1999 |
95,000 |
Abdel Moniem Mustafa Consultancy | Soil Investigation For Alsalam Road | Jabalin Provence | 1 month 2000 |
60,000 |
National Electricity Corporation | Soil Investigation For El Gaili Idd Babikir High Tension Power Transmission Line | El Gaili – Khartoum | 2 months 2000 |
62,000 |
CPECC | Soil Investigation (Pipeline crossings at Nile & Atbara Rivers | Omdurman | 1 months 2001 |
100,000 |
Sherian El Shamal Co. | Soil Investigation For Dongola El Siliam Bridge | Dongola | 2 months 2001 |
40,000 |
Sherian El Shamal Co. | Soil Investigation For Marawi Karima Bridge | Karima | 1 month 2001 |
42,000 |
Irrigation Works Corporation | Pile Foundation At Gushabi – Northern State | Northern State | 1 month 2002 |
40,000 |
Adar Construct JV. | Pile Foundation at Adar Yel Area – Upper Nile | Upper Nile State | 2 months 2002 |
60,000 |
Road & Bridges Authority – Khartoum State. | Pile Foundation for Fly over Bridge at El Ghaba & Tabia Road – Khartoum | Khartoum | 3months 2003 |
200,000 |
Gasr El Lulu Company | Pile Foundation Alamul Hospital – Khartoum North | Khartoum North | 2 months 2003 |
300,000 |
Petronac | Soil Geotechnical Investigation for : Rubkona Bridge/Pipeline River Crossing, CPF Accommodation & Manifiold. |
Block 5 A | 3 months 2004 |
300,000 |
Ofzen Co. | Soil Investigation of Ozozab-Salha and Tuti Island – Khat North Bridges | Khartoum | 21/2 Months Aug 2004 – Oct 2004 |
95,000 |
PICS Co. | Soil Investigation for Petrodar Pipe Line from Khartoum to AlJabalyen | Khartoum – AlJbalayn | 1 Month Sep 2004 – Oct 2004 |
55,120 |
Ministry of irrigation (Mewore Dam Project Implementation Unit | Geotechnical Investigation for Merowe Dam | Merowe – Karima – Sudan | 4 months 2004 |
500,000 |
PetroDar Operating Co. (PDOC) | Geotechnical Investigation for Bashayer 2 – Marine Terminal | Port Sudan | 3 Months 2004 | 70,000 |
Durch | Geotechnical Investigation for Khartoum New Airport Selection (3) Locations | Khartoum State – Gazera State. | 2004 | 80,000 |
Government & Private Locations | Different Locations for small projects | Khartoum, Northern State .etc. | 2006-2009 | 400,000 |
Total |
2,619,120 |